Sl NoInformation
1
District
BIRBHUM
Block
Bolpur (M)
GP(s)
Ward - 006
Category
Infrastructure
Sub Category
Drainage
UID
BIR001
Population Impacted
500 (approx)
Latitude & Longitude
N.A.
Issue Description
There is a need for urgent repairing of drainage and drainage slabs in gurupally
Before
02/02/2021
Progress
05/02/2021
Completion
20/01/2021
2
District
BIRBHUM
Block
Bolpur (M)
GP(s)
Ward - 005
Category
Infrastructure
Sub Category
Drainage
UID
BIR002
Population Impacted
550 (approx)
Latitude & Longitude
N.A.
Issue Description
There is a need for urgent repairing of drainage and drainage slabs in Indrapally ward 5
Before
02/02/2021
Progress
N.A.
Completion
20/01/2021
3
District
BIRBHUM
Block
BOLPUR
GP(s)
RAIPUR-SUPUR
Category
Infrastructure
Sub Category
Road
UID
BIR004
Population Impacted
1200 (approx)
Latitude & Longitude
N.A.
Issue Description
There is a need to repair the road connecting Kashipur bus stand to Supur (1 Km.)
Before
22/01/2021
Progress
22/01/2021
Completion
22/01/2021
4
District
BIRBHUM
Block
BOLPUR
GP(s)
RUPPUR
Category
Infrastructure
Sub Category
Electricity
UID
BIR007
Population Impacted
550 (approx)
Latitude & Longitude
N.A.
Issue Description
There is a need for installation of 10-15 street lights in the Binuria village
Before
22/01/2021
Progress
N.A.
Completion
02/02/2021
5
District
BIRBHUM
Block
BOLPUR
GP(s)
RAIPUR-SUPUR
Category
Infrastructure
Sub Category
Electricity
UID
BIR010
Population Impacted
900 (approx)
Latitude & Longitude
N.A.
Issue Description
There is a need to repair or replace the street lights from Aban setu to Supur Joramondir area.
Before
22/01/2021
Progress
04/02/2021
Progress
04/02/2021
Completion
24/01/2021
6
District
BIRBHUM
Block
Bolpur (M)
GP(s)
Ward - 020
Category
Infrastructure
Sub Category
Drainage
UID
BIR013
Population Impacted
1200 (approx)
Latitude & Longitude
N.A.
Issue Description
There is a need for proper drainage system in Suri Para, from the AITC party office to Panchanantala
Before
21/01/2021
Progress
N.A.
Completion
21/01/2021
7
District
BIRBHUM
Block
Bolpur (M)
GP(s)
Ward - 007
Category
Infrastructure
Sub Category
Drainage
UID
BIR014
Population Impacted
800 (approx)
Latitude & Longitude
N.A.
Issue Description
There is a need for proper drainage system from Nichu Bandhgora Masjid to west end of Mathpara. (600m -700m).
Before
20/01/2021
Progress
N.A.
Completion
20/01/2021
8
District
BIRBHUM
Block
Bolpur (M)
GP(s)
Ward - 001
Category
Infrastructure
Sub Category
Electricity
UID
BIR016
Population Impacted
700 (approx)
Latitude & Longitude
N.A.
Issue Description
Street lights are required at Goury Ashram Playground
Before
20/01/2021
Progress
01/02/2021
Completion
20/01/2021
  